Data center power, cooling, water and fire: power distribution, cooling, environment monitoring, fire safety and operations

0 articles · Collected every 30 minutes from trade media and news

Basics

  • OperationsChina

    PUE 与能效等级:GB 40879-2021

    • PUE = 数据中心总耗电 ÷ IT 设备耗电,越接近 1 越好;国际上的定义见 ISO/IEC 30134-2。
    • GB 40879-2021 把数据中心能效分为三级:1 级 PUE ≤ 1.20、2 级 ≤ 1.30、3 级 ≤ 1.50,3 级即能效限定值。
    • 标准 2021 年 10 月发布,2022 年 11 月 1 日起实施,是强制性国家标准。